skip navigation

Wavecrest Trail Extension Update: Restoration, Hydroseeding, and Parking

Work at the Wavecrest construction site has slowed due to recent rain, but steady progress continues on key elements of the project. Over the past two weeks, the contractor focused on building the second (western) parking lot and restoring eroded blufftops on the south side of the ravine.

Soil excavated from the new parking lot area was repurposed for the blufftop restoration site—about 0.3 acres where topsoil had previously washed away. After shaping the terrain for proper drainage, the team seeded the area with a native coastal mix and installed straw wattles to help prevent erosion ahead of last week’s storms.

This week will be a shorter construction week as more rain is expected. The south bluff restoration area is being hydroseeded—a process that sprays a slurry of water, native seed, mulch, and nutrients to quickly establish vegetation and stabilize the soil. The mixture may include a biodegradable colored dye, which helps crews see where the seed mix has been applied; the color fades naturally over time and is completely compostable.

Meanwhile, the contractor will begin connecting the existing casual path to the redwood crib wall structure, creating a temporary route for informal beach access from the south side. This interim path will remain in place until construction begins on the permanent south staircase, anticipated to start in January.

As always, thank you for your continued patience and support as this exciting project nears completion—bringing improved access and restored habitats to our beloved coastal landscape.